Sablich Center reopens in September

  • Published
  • By Susan Griggs
  • 81st Training Wing Public Affairs
Once changes to fire suppression, electrical, mechanical and furniture requirements are completed, Sablich Center reopen in September. 

Before Hurricane Katrina struck Keesler 23 months ago, Sablich Center was the heart of Keesler's support activities. Since Katrina, offices and agencies have been scattered at several base locations while damage from storm water intrusion from the roof and windows is repaired. 

The $6.2 million restoration project was originally scheduled for completion April 30. About 75 percent of the work has been done so far, according to Dave Horner of the 81st Civil Engineer Squadron's program management office. 

"We're negotiating modifications for the project," Mr. Horner explained. "Now we expect to complete the work in mid-summer and open the building for occupancy in September."
Mr. Horner said most of the modifications involve the electrical system. Electrical codes have changed several times since the facility was constructed, and upgrading the wiring is a matter of safety and economics. 

"We had reports that the system wasn't sufficient to keep up with the building's growing demands before the storm, so we're upgrading that now," he commented. "Wiring has to be upgraded to support new mission requirements." 

Another part of the building modernization effort has been the installation of a fire suppression system throughout the building, which didn't have a sprinkler system before Katrina. 

In addition to the electrical improvements, interior work continues and three new roof-mounted air handling units were recently installed. 

Mr. Horner added that a TIGER Team representing all of Sablich Center's intended users and operational groups is addressing furniture, requirements and functional needs. 

"The team meets every two to three weeks to discuss ongoing challenges so we'll have a complete and up-to-date facility," Mr. Horner stated. "We know people are anxious to be back in the building, and we're working hard to make that happen as soon as possible.